July 2018 Building Improvement Fund2018 Building Improvement Fund (CIP) - Fund 5200
2018 July YTD
Budget Total Actual Remaining
Revenues:
Transfer from General Fund 350,000 350,000 350,000 0 (1)
Interest Earnings (allocated at year end)7,718 0 0 (7,718)
Total Revenues 357,718 350,000 350,000 (7,718)
Expenditures:
Project Name
5211 Carpet Replacement-City Buildings 30,000 0 19,880 10,120
Generators 35,000 0 0 35,000
Air Compressor 10,000 0 0 10,000
5215 Installation of Building Security Systems 30,000 1,476 17,634 12,366
5201 Public Buildings Roof Replacement 270,000 8,466 33,785 236,215
5208 Workstation Replacements 40,000 2,784 47,786 (7,786)
Window Replacements-Various Buildings 25,000 0 0 25,000
Total Expenditures 440,000 12,726 119,085 320,915
(1)Transfer were made in June.