13-Appendixcity 0
golden
va e
Capital Improvement Program 2020-2029
Appendix Section
Exhibit A
Special Assessment Policy
for
The City of Golden Valley
January 17, 1995
Amended February 21, 1995
Amended June 7, 2005
Amended July 18, 2006
Amended January 20, 2009
General
Minnesota State Law, Chapters 429.010 to 429.11, provides municipalities the ability to
make public improvements such as installation of sanitary sewer, water, storm sewer,
sidewalks, and street improvements (including grading, curb and gutter, surfacing, and
lighting). The procedures that Cities must follow, including reports, notices, and public
hearings, are well defined within the laws.
The Statute allows municipalities to assess all or portions of the costs of any
improvements to property owners based on the benefits received from the project. The
Statute is not specific regarding the determination of benefits to a property, or how to
apportion the costs to the benefiting properties. Rather, the law makes the municipality
responsible for developing an equitable method of cost sharing among the benefiting
property owners.
The purpose of this special assessment policy is to provide a guide, to be used by City
Staff, for preparing assessment rolls for approval by the City Council. This policy is
meant to assure uniform and consistent treatment to all properties within the City as
improvements occur.
The special assessment policy will not cover all possible assessment situations. Special
cases and variations of standard cases that are not specifically discussed under this
policy will be evaluated during preliminary project studies, and assessments will be
determined that do not violate the benefit principles as required by Statute.
No special assessments will be levied against designated floodplains, municipal storm
water ponds or wetland areas on private property as determined by criteria in the
Wetland Conservation Act of 1991 and the Minnesota Department of Natural
Resources. The limits of wetlands will be determined by the City on a case-by-case
basis at the time of preliminary project design and feasibility report preparation.
No special assessments will be levied against railroad, county highway or state highway
rights-of-way. Properties fronting County Roads and County Highways will be subject to
special assessments for reconstruction projects based upon this policy.
Special assessments levied by the City will include an administrative fee, to be
established annually by ordinance, to finance indirect costs associated with the
assessment that are incurred by the City.
Sanitary Sewer and Water Main Assessments
Reconstruction and Repairs
No special assessments will be levied for repair and reconstruction of existing
sanitary sewer and water main systems, except for properties that have not been
previously assessed for these utilities.
For properties not previously assessed that are adjacent to sanitary sewer or
water main reconstruction projects, the amount of special assessments will be
calculated on a case-by-case basis at the time of preliminary design and
feasibility report preparation.
Property owners are responsible for maintenance, repair and replacement of
sanitary sewer services from, and including the connection to the main, and the
building being served. Pavement Management street reconstruction projects will
include an opportunity for property owners to reconstruct or repair their sanitary
sewer services. All costs, including construction, administration and other indirect
costs, will be specially assessed to the property being served by the sanitary
sewer service.
The City is responsible for maintenance, repair and replacement of water
services from the connection to the water main up to and including the curb stop
or valve on the service line. The property owner is responsible for maintenance,
repair and replacement of the water service from the connection of the service
pipe to the valve or curb stop, to the building being served.
New Construction
In instances where property is developing or redeveloping, public sanitary sewer
and water main may need to be installed. The construction of City sanitary
sewer, water mains and storm sewer to serve these properties will be
constructed as public improvement projects, unless the City opts to have the
developer design and construct the improvements. The developer of such
properties will be responsible for the entire cost of public utilities, including
construction, administration and other indirect costs, whether construction is
performed as a City Improvement Project or by the developer.
At the time such a development project is proposed, the Public Works
Department will determine if the project is to be constructed publicly or privately.
If the utility installation is to be constructed privately, the developer will be
responsible for preparing construction plans and specifications consistent with
City standards. These construction plans and specifications must be reviewed
and approved by the Public Works Department. The utility installation must also
be inspected by the Public Works Department during construction. The
developer will be responsible for 100% of the costs of City construction
observation and plan review, which will be billed directly to the developer. Any
unpaid costs incurred for these services will be assessed against the developing
properties. An irrevocable letter of credit must be posted by the developer in an
amount equal to 150% of the estimated construction costs to ensure timely
completion of the project.
If a public sanitary sewer or water main project is to be installed as a City
Improvement Project, the developer will be responsible for 100% of the direct
and indirect costs incurred by the City. These costs may include, but are not
limited to: feasibility report preparation, preliminary survey, preliminary design,
final design, construction staking, construction observation, as-built surveying
and drafting, and administrative and legal costs. The developer may elect to
have these costs assessed against the property being developed or pay the
costs directly to the City.
Storm Water Drainage
Street Storm Sewer
No special assessments will be levied for construction or reconstruction of storm
sewer systems within the City right-of-way as part of the Pavement Management
Program. However, in instances where storm sewer construction is incorporated
into Pavement Management Projects to resolve rear yard drainage issues, as
discussed in this policy, the costs associated with these improvements will be
specially assessed to the benefiting property owners.
In instances where storm sewer installation is required for development and
redevelopment projects, it shall be specially assessed to the property being
developed according to the Sanitary Sewer and Water Main Assessments
section of this policy.
Rear Yard Storm Sewer
In certain instances, storm sewer is necessary in rear yard areas to correct
existing drainage problems. City staff will visit such problem areas at the request
of a homeowner to evaluate the situation and provide engineering assistance to
encourage property owners to remedy the drainage problems without City
involvement.
If a property owner or owners cannot remedy the rear yard drainage problems,
they may petition the City for installation of storm sewer. Upon receiving a
request for petition for rear yard storm sewer, engineering staff will determine the
properties that contribute storm water runoff to the problem area. The petitioner
must then circulate the petition to the contributing property owners for signatures.
Each contributing property owner must be made aware that special assessments
will be levied against their property for the corrective storm sewer work. A
minimum of 35% of the contributing property owners must sign the petition for
the City Council to consider the project. Upon receipt of the petition and after a
public hearing, the City Council may either deny the request or order the storm
sewer improvements. If the improvements are ordered, the contributing property
owners will be assessed for 100% of the construction and indirect costs for the
storm sewer installation. The method of assessment and the pro-ration of costs
will be determined on a project-specific basis.
Affected property owners in rear yard drainage projects will also be required to
dedicate all drainage and utility easements for the installation of the storm sewer
at no cost to the City. If the City must purchase or condemn in order to obtain the
easements, the entire acquisition costs will be included in the project costs for
assessment or the City may decline to undertake the project.
Street Improvements
Development/Redevelopment Projects
When property is developed or redeveloped that has street frontage on
roadways that are scheduled for construction or reconstruction, the development
will be required to pay an escrow for the future street rehabilitation. The escrow
shall be based upon the assessment methods and land uses contained in this
policy, and shall be based on the assessment rates in effect at the time the
development is approved. The property or properties within the development will
not be specially assessed at the time street rehabilitation occurs.
Sidewalks
No special assessments will be levied for sidewalk construction that is in
accordance with the goals and recommendations of the City of Golden Valley
Sidewalk Committee. Requests for sidewalks that are not on the current
Sidewalk and Trail Plan will be forwarded to the Sidewalk Committee for
consideration. The Sidewalk Committee will forward its recommendations for the
requested sidewalks to the City Council, which will determine if the proposal
should be included in the Sidewalk Plan.
Street Lighting
Street lighting is available to the residents of Golden Valley on a petition basis
according to the Street Lighting Policy.
New Street Construction
As property within the City develops or redevelops, it may be necessary to install
public streets. The Public Works Department will determine if the project is to be
installed publicly or privately. The procedures, policies, and requirements for
street construction will be the same as discussed for new sanitary sewer
installations.
Sealcoating
No special assessments will be levied for street sealcoating.
Bituminous Milling and Overlays
No special assessments will be levied for bituminous milling and overlays.
Street Reconstruction
Special assessments for street reconstruction projects will be in accordance with this
policy and Minnesota Statutes, Chapter 429. The total amount of the special
assessments will be a minimum of 20% of the street reconstruction costs not to exceed
the benefit received by each property. Special assessment rates for all land uses and
street classifications will be determined annually by ordinance.
Local Streets
1. Properties with residential and duplex residential land use, parks and other City-
owned properties subject to reconstruction will be assessed on a per-unit basis,
with one unit assessed to each property unless the property has the potential to
be further subdivided into two or more lots that each meets City subdivision
ordinance requirements. Such lots that may be so subdivided shall be assessed
for the number of units that equals the number of such lots that the property may
be subdivided into. However, residential properties that are subject to multiple
unit assessments will have all but one of such unit assessments deferred at the
time of the initial assessment. Such deferral will be made each year until such
time as the property is subdivided. At that time, the deferred unit assessments
shall be due.
2. Special assessments against properties with Multiple Dwelling land use will be
on a front-foot basis, with 100% of the frontage being improved subject to
assessment.
3. Properties with church, school and other tax exempt land uses will be assessed
on a front-foot basis, with 100% of the frontage being improved subject to
assessment.
4. All other land uses, including commercial, industrial, business and offices will be
assessed on a front-foot basis, with 100% of the frontage being improved subject
to assessment.
5. Residential properties adjacent to local streets being reconstructed may
participate in voluntary programs to have their driveways reconstructed and
sanitary sewer service repaired or reconstructed at contract unit prices.
Residents will be notified of these programs at informational meetings for each
street project. If a resident participates in these programs, staff will coordinate
construction with the contractor and will measure the quantities installed. The
construction costs, along with an administrative fee, established annually by
ordinance, will be assessed to the property owner.
6. When a corner residential lot has frontage on two local streets, it will be
assessed for one-half unit assessment for each street subject to reconstruction.
No more than one total unit assessment will be charged against a parcel for
street reconstruction. Corner properties adjacent to State Aid and local streets
will be charged one-half of the appropriate unit assessment at the time of
reconstruction of each street.
7. Corner residential properties adjacent to a local street and a state or county
roadway will not be subject to special assessments by the City for state highway
or county road reconstruction. However, these properties will be assessed the
appropriate number of unit assessments for the entire frontage along the local
streets when reconstruction occurs on the local street.
8. Residential properties adjacent to frontage roads of state highways will be
considered to be on local or Municipal State Aid streets and will be assessed
consistent with this policy.
9. Special Assessments for properties not specifically covered in any of the above
cases will be addressed on a parcel-specific basis at the time of the feasibility
report.
State Aid Streets
1. Properties with residential and duplex residential land uses that have frontage on
a Municipal State Aid Street will be assessed on a per-unit basis. The per-unit
assessment rate will be approximately 25% of the standard residential rate for
properties on local streets. Assessments for oversized parcels with the potential
for subdivision are to be consistent with the previously discussed policy for local
streets.
2. Properties with Multiple Dwelling land use that front on a Municipal State Aid
Street will be assessed on a front-foot basis for the frontage being improved.
Properties with church, school, and other tax-exempt land uses that front on a
Municipal State Aid Street will be assessed on a front-foot basis for the frontage
being improved.
All other land uses, including commercial, industrial, business and offices that
front on a Municipal State Aid Street will be assessed on a front-foot basis for the
frontage being improved.
3. Special assessments for properties not specifically covered in any of the above
cases will be addressed on a parcel-specific basis at the time of the feasibility
report.
4. Residential properties adjacent to State Aid streets being reconstructed will be
given the option of having their driveways and sanitary sewer services repaired
or reconstructed under the same terms discussed in the local street
reconstruction portion of this policy.
County Roads
1. Properties with residential and duplex residential land uses adjacent to county
roads will be assessed according to the previously discussed methods for local
streets, except for corner lots with local streets, which will be assessed in full at
the time the intersecting local street is reconstructed. Special assessments to
residential properties will be at State Aid street rates.
2. All other land uses, including commercial, industrial, business, and tax-exempt
uses will be assessed on a front-foot basis, with 100% of the frontage being
improved subject to assessment. The assessment rate shall be the rates used
for State Aid streets as established by ordinance.
Low Income Senior Citizen and Disability Deferments
As required by Minnesota Statute, the City has a special assessment deferral policy for
low income senior citizens and disabled persons meeting all of the following criteria:
1. The property upon which the assessment is deferred must be homesteaded;
2. The property is owned by a person at least 65 years of age on January 1 st of the
year in which payment of the first installment of the subject assessment is due; or is
owned by a person who is retired due to permanent and total disability.
3. The applicant must have a "financial hardship" defined as:
a) An annual income at or below a level established annually by ordinance and;
b) The aggregate total of all special assessments levies will exceed one and one-
half percent (1-1/2%) of the applicant's annual income.
More information is available at General Services Office (763.593.8020).
Street Reconstruction Special Assessment Rates
Special assessment rates as discussed in this policy will be established yearly with the
Annual Fee Resolution. The rates will be based on the percentages of construction and
indirect costs as discussed above. Indirect costs are estimated to be 30% of the
construction costs and include administration, engineering, construction observation,
and legal fees. These rates will be subject to revision each year based on the actual
construction costs in the City from the previous year and for inflation based upon the
ENR Index for construction costs.
city ofI%
goldvenlley
Fleet Operation ,
Maintenance , and
Replacement Policy
Message from the Manager
Motor vehicles and equipment are vital to day-to-day operations and service delivery
activities of the City of Golden Valley. The Public Works Department Vehicle
Maintenance Division is responsible for the stewardship of the City's fleet and
equipment assets and for meeting the fleet and equipment service requirements of City
departments. The division also develops fleet and equipment utilization and
replacement policies and schedules. The Vehicle Maintenance Division is an internal
service division of the Public Works Department of which the costs are allocated to the
other City departments for services provided.
The main goal of the Public Works Department Vehicle Maintenance Division is to
provide vehicles that are dependable, flexible, efficient, and responsive so that City
departments and divisions can operate in a cost-effective manner, minimizing the City's
vehicle equipment budget. The division is also committed to maintaining the City's fleet
and equipment so that the equipment is readily available for performing City operations
and keeping downtime to a minimum. The Public Works staff works with all departments
to embrace a philosophy which emphasizes the value of the importance of vehicle and
equipment availability, safety, reliability, and efficiency as well as preserving the City of
Golden Valley's major capital investment in fleet and equipment.
The City has established a capital replacement schedule to replace aging vehicle and
equipment. The vehicle and equipment replacement schedule, in conjunction with the
5-year Capital Improvement Program (CIP) and operating budgets, is used to plan any
major capital investment (the CIP reflects only those investments that exceed $10,000).
New equipment or other items, which are not part of a replacement schedule, are
funded annually out of the originating or requesting department's operating budget.
Approved February 2010
Purpose
The purpose of this policy is to assign responsibility to the City of Golden Valley's Public
Works Department Vehicle Maintenance Division for the operation, maintenance,
acquisition, and replacement of vehicles and equipment owned and operated by the
City, with the exception of vehicles and equipment used by Brookview Golf Course,
which are acquired, operated, maintained, and replaced by Golf Maintenance.
Policy
This policy is intended to ensure the availability of funds for the operation, maintenance,
acquisition, and replacement of fleet and equipment. Adherence to this policy will
provide effective and efficient fleet and equipment services for operating
departments/divisions to provide the best services for the residents and businesses of
Golden Valley. This policy establishes a sound business approach associated with the
evaluation of vehicle and equipment cost and capabilities, purchasing and funding
methodology, and making decisions on acquisition and replacement considering the
level of usage and demonstrated needs. Departments are asked to review vehicle and
equipment needs with a goal of increasing fuel efficiency, consideration of alternative
and/or flexible fuels, reducing the number of vehicles, conversion of the diesel vehicle
and equipment to bio-diesel, and promoting the anti-idling policy.
1. Vehicle and Equipment Replacement
A vehicle and equipment replacement schedule is maintained by the Public Works
Department Vehicle Maintenance Division and Finance Department. Replacement of
vehicle and equipment will generally follow the attached Equipment and Vehicle
Replacement Guidelines and are summarized as follows and listed as Attachment A:
a. Description
b. Unit number
c. Classification
d. Year purchased
e. Purchase price
f. Expected service life
g. Projected replacement cost
h. Annual fuel, maintenance, and overhead costs by vehicle classification
2. Vehicle and Equipment Maintenance
Vehicle and equipment preventative maintenance schedules are maintained by the
Public Works Department Vehicle Maintenance Division with the goal of keeping
vehicles and equipment available 95% of the demand time.
a. Generally, maintenance standards and procedures are as recommended by the
vehicle/equipment manufacturer or other recognized authority, or utilizing the
Public Works Department Vehicle Maintenance Division Preventative
Maintenance Schedules.
i. Daily maintenance inspections are performed by operators and
maintenance personnel using the Pre-operation Inspection Form.
ii.Scheduled maintenance is performed by the maintenance mechanics
considering the above-referenced Preventative Maintenance Schedules.
iii. Demand maintenance is generated by user activities and may require
outside services. The Service Request Form is used to request demand
maintenance.
iv. All maintenance done by the operator shall be coordinated with the
Vehicle Maintenance Division.
b. The Public Works Department Vehicle Maintenance Division may remove
equipment or vehicles from service based on the Commercial Vehicle Safety
Alliance (CVSA) Out-of—Service Criteria (OSC) or other recognized criteria.
3. Vehicle and Equipment Operation
The use of City vehicles or equipment is approved only for matters related to City job
responsibilities or for City business. Operation of City vehicles and equipment shall
be in accordance with the Employee Handbook, Section 5.0, Subd. 5.25, Vehicle
Use, January 1, 2006. Care and cleaning of vehicle and equipment is the
responsibility of the user.
The Public Works Department Vehicle Maintenance Division will manage and
maintain the central fuel system. This includes fuel system access assignments and
records management.
a. Dedicated department vehicles shall be assigned to departments whose job
duties require the immediate availability of a vehicle.
i. Dedicated vehicle use shall be subject to the same limitations and
conditions as identified in the Vehicle Use Policy.
b. Shared vehicles should be considered for employees with similar job duties and
should be considered in lieu of a dedicated vehicle.
Funding
Vehicle and equipment replacement will be funded through the CIP. The Public Works
Department Vehicle Maintenance Division will maintain a current and complete
inventory of all vehicles and equipment in coordination with all users and the Finance
Department. These inventories will establish all divisions/department vehicle and
equipment replacement schedule. All vehicles and equipment maintained by the Vehicle
Maintenance Division will be reviewed on an annual basis for replacement. If a
department/division has requested replacement or an addition to the fleet, Vehicle
Maintenance will make a recommendation on the purchase for the CIP to the City
Manager. The CIP will be presented to the City Council for consideration and approval
during the budget process.
1. Funding New and Replacement Vehicles and Equipment
Fleet and equipment projected for replacement, or additional vehicles and
equipment, will be funded through the CIP process. Upon acquisition, all fleet and
equipment purchased shall be included in the vehicle and equipment inventory
database. Requests for fleet and equipment replacement will be addressed through
the normal budget process.
a. Fleet and equipment with a value in excess of$10,000 purchased for the first
time must be included in the CIP.
b. Fleet and equipment with a value less than $10,000 purchased for the first time
does not have to be included in the CIP, but must be included in the operating
budget.
2. Funding of Operational Expenses
a. Fuel Allocation
Fuel is allocated based on usage by each piece of equipment or vehicle and
billed monthly to the responsible department. Pricing for fuel is based on average
total cost of inventory and an overhead charge, as set by the Finance
Department.
3. Reassigned Equipment
a. Reassigned equipment may be used in lieu of new vehicles/equipment with
written approval by the City Manager. Reassignment duration will be as
determined annually by the Public Works Department Vehicle Maintenance
Division. Reassignments moved within or across departments/divisions will be
charged for conversion costs to the receiving department/division by internal
service charges. Reassignments with no conversion costs will not be charged.
The Finance Department will be notified of all reassignments for fixed assets and
insurance reports.
4. Equivalent Replacement/Upgrades
a. The CIP fund is structured to replace each vehicle or piece of equipment with an
equivalent unit, unless specified/justified, during the budget process.
b. Cost increases due to upgrades, changes in type of fleet or equipment, addition
of options, or other upgrades associated with vehicles scheduled for
replacement, shall be highlighted and clearly summarized as an element of the
CIP by the department requesting the upgrade or addition in options.
Responsibilities
1. Department Directors shall be responsible for:
a. Ensuring that all vehicles and equipment for replacement requests are of the
appropriate type and have only those items/options that are operationally
required.
b. Submitting requests for replacement with cost estimates to the Finance
Department and the Public Works Maintenance Manager prior to the CIP and
budget process.
2. The Public Works Department Vehicle Maintenance Division shall be
responsible for:
a. Submitting a 5-year Capital Improvement Program to the Finance Department
and City Manager during the budget process.
b. Reviewing replacement schedule annually with departments during the budget
process to ensure all vehicles and equipment are replaced as appropriate.
c. Establishing the Vehicle and Equipment Replacement Schedule.
d. Tracking fuel, labor and repair parts annually, and provide this information to
Finance and responsible departments.
e. Identifying the actual historical cost and variations in cost performance based on
lifetime-accumulated age and usage of the various vehicle and equipment types
classifications).
3. The Finance Department shall be responsible for:
a. Completing an analysis and reconciliation of the vehicle replacement CIP on an
annual basis.
Purchasing and Disposal
1. Purchasing Procedures
a. New vehicles and equipment will be purchased by the Public Works Maintenance
Manager, as assigned by the Director of Public Works and in accordance with
Minnesota Statute 471.345. Acquisitions require the cooperation and assistance
of many departments.
b. When possible, purchases will be made from the State of Minnesota, Hennepin
County, or other Joint Purchasing Agreement contracts, as permitted by State
Statute. These purchases will also follow the City's purchasing policy.
c. Details for budgeting will be provided by the Finance Director when providing the
overall budget guidelines.
2. Equipment Disposal
a. Disposal of equipment shall be in accordance with the City's business standard
of disposing all vehicles and equipment by auction, trade-in, or other approved
methods.
b. When vehicles and equipment are replaced, there may be reassignment of
vehicles or equipment, but there will be no fleet or equipment hold over on the
fleet after a replacement is purchased. Adding fleet or equipment to the inventory
without City Manager authorization is not permitted.
c. In order to address the seasonal or short-term needs, fleet or equipment may be
retained temporarily for a period not to exceed nine months from the date the
replacement fleet or equipment is placed into service.
Request for Vehicles, Equipment, and Service
1. Requesting Vehicles or Equipment
a. New vehicles or equipment in excess of $10,000 must be made and approved
through the CIP budget process, and have a life of more than three (3) years.
The request shall be discussed with the Public Works Maintenance Manager and
Vehicle Maintenance Division to avoid duplication of equipment and to discuss
the appropriate type and size of vehicle or equipment requested.
b. Request for new vehicle or equipment less than $10,000 must be made and
approved through the normal budget process.
2. Repair and Maintenance of Vehicle or Equipment Requests
a. All repair and maintenance of vehicles and equipment will be made by
completing the Vehicle Maintenance Repair Slip, as provided by the Vehicle
Maintenance Division.
Acquisition Request(s)
The 5-year CIP will be reviewed and evaluated annually as part of the budget process.
In any given year, vehicle or equipment originally planned for replacement may be
adjusted as necessary to account for current needs.
city 0
old e n
valle Y
VEHICLE AND EQUIPMENT REPLACEMENT GUIDELINES
Public Works Department Vehicle Maintenance Division Management
Methodology
To manage the City's fleet in a manner that theoretically all of the City's motorized
equipment and vehicles are maintained and disposed of by the Public Works
Department Vehicle Maintenance Division. The Vehicle Maintenance Division has full
responsibility for vehicle and equipment maintenance and the equipment users are
charged an hourly repair rate for all service and repairs.
1. Expected Life
When new vehicles or equipment are purchased, it is given an expected life (years
in service) based on a variety of factors. Below are the estimated life expectancies
for some of the significant pieces of equipment:
a. Engine Pumpers 20+ years (refurbish half way through life cycle)
b. Tandem Dump Trucks 12 years
c. Single Axle Dump Trucks 12-14 years-some longer
d. Wheel Loaders 15-18 years
e. Backhoe/Excavators 10-12 years
f. Jet Truck 10 years
g. One-Ton Trucks 9-10 years
h.
3/
and '/2 Ton Pickups 10 years-some longer
i. Skid Steers 8-10 years
j. Street Sweeper 8 years
k. Tractors Varies (15 years average)
I. Vactor Truck 10 years
m. Mowers Varies (6-10 years)
n. Sport Utility Vehicle 10 years
o. Passenger Cars/Vans 10 years
p. Squad Cars 100,000 miles/4 years
q. Trailers 15 years
r. Sidewalk Machines 10-12 years
2. Replacement Factors
When a particular piece of vehicle or equipment achieves its expected life and
reaches its anticipated replacement year, it is analyzed to determine if it should be
replaced based on the following factors:
a. Critical nature of the equipment or vehicle and the availability of a backup or
alternative equipment or vehicle. For example, the Sewer Jet is a critical piece of
equipment for which there is no backup except to contract for those services. It is
important to have this equipment operational with minimal downtime.
b. Use of the equipment or vehicle (hours and/or miles). The duration and intensity
of use are also important factors. For example, squad cars typically achieve their
expected life of 100,000 miles and are retired in approximately 4 years while
other vehicles (cars and light trucks) may never achieve 100,000 miles and can
last for many years.
c. Appropriateness of the equipment or vehicle for the assigned tasks. Public Works
and the user examines whether the equipment or vehicle is still capable of doing
its intended work, whether it is the right equipment, and determine if the work
changed causing the equipment or vehicle to be obsolete.
d. Repair history, costs, and downtime. Mechanics provide critical input and
assessments of the overall condition of the equipment. Near the end of the
expected life of the equipment or vehicle, repair costs can exceed the value of
the equipment or vehicle and replacement is appropriate.
e. Suitability of the equipment or vehicle for other tasks. Other departments provide
input regarding the ability to reassign equipment and vehicles to other less
frequent or intense duties. For example, Public Works have re-assigned used
marked squad cars and light pickup trucks to other departments.
3. Life Cycle Costing
This accounting method is used as much as possible in managing the City's fleet
management. Life cycle costing includes the purchase cost of the equipment or
vehicle, lifetime maintenance and operation costs, and the residual value at the time
of disposal. This is the true cost of equipment or vehicle ownership. The goal is to
replace the equipment during its economic life. This is the period when the
maintenance costs are the lowest.
4. Fire Department Vehicle Replacement Practice
Fire apparatus is historically refurbished half way through its life cycle
approximately 10-12 years) and replaced after 20 to 24 years of service, or a couple
of years longer depending on condition. This general rule applies to "major"
apparatus, engine, and ladder trucks. The replacement of a particular piece of
apparatus is based upon several factors including the general mechanical and
structural condition, required vehicle and safety upgrades, technological changes,
current and anticipated use, anticipation of future mission changes, and the current
mechanical history (including mileage).
The apparatus replacement schedule is revised to reflect a philosophy of validating
the replacement of a vehicle, as opposed to replacement based solely upon the age
of the vehicle. To this end, vehicles have been moved back in the replacement
schedule and not replaced at the time mark historically associated with replacement
schedules. Refurbishing pumpers and ladders to extend the "life" of fire apparatus is
a common practice. Refurbishing pumper and ladder fire vehicles extends vehicle
life.