2021-05-05JOINT WATER COMMISSION MINUTES
Golden Valley - Crystal - New Hope
Meeting of May 5, 2021
The Golden Valley — Crystal — New Hope Joint Water Commission (JWC) meeting was called to order at
1:30 pm.
Roll Call
Present
Anne Norris, City Manager, Crystal
Kirk McDonald, City Manager, New Hope
Tim Cruikshank, City Manager, Golden Valley
Staff Present
Joe Hansen, Utilities Supervisor, Golden Valley
Dave Lemke, Operations Manager, New Hope
Matt Rowedder, Utilities Maintenance Supervisor, New Hope
Patrick Sele, Utilities Supervisor, Crystal
Tim Kieffer, Public Works Maintenance Supervisor, Golden Valley
Sue Virnig, Finance Director, Golden Valley
Bernie Weber, Public Works Director, New Hope
Derek Goddard, Golden Valley
Mark Ray, Director of Public Works/City Engineer, Crystal
R.J. Kakach, Assistant Engineer, Golden Valley
Carrie Nelson, City of Golden Valley
Approval of Minutes — April 7, 2021
Moved by McDonald seconded by Cruikshank to approve the minutes of the April 7, 2021 Joint Water
Commission (JWC) Meeting. Upon a roll call vote the following voted in favor: Norris, McDonald, and
Cruikshank. The following voted against: None. Motion carried.
Receive and File the 2020 Financial Statement and Management Correspondence
Staff reviewed and answered questions regarding the 2020 Financial Statements and 2020 Management
Letter from MMKR Certified Public Accounts.
Moved by Cruikshank seconded by McDonald to receive and file the 2020 Financial Statement and
Management Letter. Upon a roll call vote the following voted in favor: Norris, McDonald, and
Cruikshank. The following voted against: None. Motion carried.
Update on North Water Tower Proiect Including Approval of Stantec Consulting Services Request for
Additional Funds
Staff is requesting the Commission approve additional costs for Stantec Consulting Services, Inc. for the
coordination of quotes on driveway repair, inspections, and closeout after November 2019. The driveway
and restoration work was originally part of the New Hope North Water Tower Bypass Project.
Joint Water Commission
May 5, 2021
Page 2 of 2
The contractor, Osseo Construction Company LLC has completed the work on the project. However, the
contract completion dates was November 1, 2018 and the contractor did not complete work on the
elevated tank until 2019. These delays resulted in additional costs.
Site work improvements related to driveway and restoration work were needed at the elevated tank. This
site work was originally included with the 2018 North Water Tower Bypass Project. Because of the delays
associated with the painting of the elevated tank, the site work improvements were deleted from the
Bypass Project and added to the Elevated Tank Rehabilitation Project. Quotes were received to complete
that site work in 2019 and the work was completed in 2020 by Omann Brothers, Inc.
The final payment to Osseo Construction was reduced by $50,132.50 to cover additional costs associated
with Stantec Consulting and Omann Brothers driveway and restoration costs.
The additional Stantec costs from what was reviewed in November 2019 is $38,023.24 less $32,578 leaves
$5,445.24 additional costs.
Moved by Cruikshank seconded by McDonald to approve the increase of Stantec Consulting agreement for
the 500,000 Gallon Water Elevated Tank Rehabilitation Project in the amount of $5,445.24
TAC Update
Staff provided an update from the April 30, 2021 TAC meeting.
Other Business
Commissioners requested staff to invite Bolton and Menk, Incorporated to the next scheduled Joint Water
Commission Meeting scheduled for June 2, 2021 for a presentation on the Reservoir (North Tank) Reality
Capture Data.
The next Joint Water Commission meeting is scheduled for June 2, 2021
Adiournment
Moved by McDonald seconded by Norris to adjourn meeting. Motion carried.
Chair Norris adjourned the meeting at 2:30 pm.
ATTEST:
Sue Schwalbe, Recording Secretary