#411 09-05-72 Approve Manner of Construction 72-WM-12295
Resolution No. 111 September 5, 1972
Member Stockman introduced the following resolution and MOVED its adoption:
RESOLUTION APPROVING PLANS AND SPECIFICATIONS
AND ORDERING MANNER. OF CONSTRUCTION
72-WM-12
WHEREAS, the Village Engineer has prepared plans and specifications for
the above proposed public improvement construction and has presented such
plans and specifications to the Council for its approval;
NOW THEREFORE, BE IT RESOLVED by the Village Council of the Village of
Golden Valley:
1. That all of such plans and specifications are hereby approved.
2. That with respect to all of the public improvements referenced above,
excepting therefrom only those noted below, the Village Clerk shall prepare
an Advertisement for Bids for making such improvements under such approved
plans and specifications. The advertisement shall be published as required
by statute, shall specify the work to be done and shall state the time and
place that the bids shall be opened and considered by the Village Manager and
Village Clerk.
NONE
3. That there is hereby excepted from the force and effect of the fore-
going resolution the following public improvement(s):
NONE
4. That as respects the following public improvement(s):
NONE
it is hereby found and determined that the Village of Golden Valley has
sufficient equipment to carry on the work necessary for said improvements.
It is hereby directed that said equipment be used for said work and that
the appropriate funds shall be charged for the use of said equipment and the
reasonable rental value thereof as the cost of said work, and the Village
Engineer shall keep an accurate record and account of the use and rental of
said equipment and of materials used and of work done and shall include it
on any and all reports on the cost of work done by day labor under the pro-
visions of the resolution. Therefore, the Village Engineer shall proceed
under the direction of the Village Manager to carry on all work in connection
with said improvement, in accordance with the plans and specifications here-
inabove approved.
5. That as respects the following public improvement(s):
72-WM-12
296
Resolution No. till September 5, 1972
the same does not, on the same price basis, exceed twenty-five percent (25%)
of the original contract price of that certain contract entered into on
September 18, 1972, with White Construction Company, Inc. for public improve-
ment 72-Tn1Nf-12 awarded on a unit price basis with a total contract amount of
$32,045.15. Therefore, the Mayor and the Village Manager are hereby authorized
to change the contract of September 18, 1972, with White Construction Company,
Inc. for public improvement 72-WM-12 so as to include the additional units of
work at the same unit price providing for the construction of public improvement
72-WM-12 when the said contractor shall have furnished the contractor's bond in
the amount of the additional work as required by law.
Attest:
Village Clerk
Mayor
The motion for the adoption of the foregoing resolution was duly seconded by
Member Hoover, and upon vote being taken thereon, the following members voted
in favor thereof: Hoover, Paulson, Riggs, Stockman, and Ulstad; and the
following voted against the same: None, whereupon said resolution was de-
clared duly passed and adopted, signed by the Mayor, and his signature attested
by the Village Clerk.
11